Thirty men take 20 days to complete a job working 9 hours a day. How many hours a day should 40 men work to complete...

Solution

Number of man hours required to complete the job is = 30 × 20 × 9 = 5400 Number of hours a day should 40...

Register & Unlock access to Prep for free

Save & Analyse
your Practice

Learn, Practice &
Improve fast

Improve your
Accuracy

Track & Improve
Scores in all Topics

Session Time
Tracker

Review your
Performance

Insights on others
Performance

View Performance
Reports

Achieve your
Target

Flexible Learning &
Practice

Question Time
Tracker

Improve your
exam scores

Solution

.hez-title-solution{display: none;}

Keynote

#hez-keynote-title{display: none;}

Study the table and answer the following questions

|||||||||

Mayur weighs twice as much as Shweta. Shweta’s weight is 60% of Deepika’s weight. Rakesh weighs 50% of Vikas’s weight….

|||||||||||

Read the given data carefully and answer the following questions Four friends A, B, C and D are studying together in class 12th. A and B…

||

0 Time & Work questions available for your Free Practice
0 Quantitative Ability questions available for your Free Practice
Practice 0 questions for Free
Scroll to Top