Number of man hours required to complete the job is
= 30 × 20 × 9 = 5400
Number of hours a day should 40...
Register & Unlock access to Prep for free
Solution
.hez-title-solution{display: none;}
Keynote
#hez-keynote-title{display: none;}
0
Time & Work questions available for your Free Practice
0
Quantitative Ability questions available for your Free Practice
General AwarenessFill in the BlanksRBIGeometrySentence ImprovementLogical ReasoningAPPSCTaglinesTime & WorkLogarithmsProgressions & SeriesDirectionsCircular ArrangementCoding & DecodingNumber SeriesGMATClocks & CalendarsMathematical InequalitiesInequalitiesIBPSTCSLICNMATAveragesMiscellaneous - QAProfit and LossAnalogiesEnvironment & BiodiversityMixtures and AllegationsQuadratic RelationsPie ChartLine GraphsCMATSimple EquationsData InterpretationMensurationData ProblemsMiscellaneous - GAMATCaselet DIBar GraphsNumbersCATNumber SystemFunctionsSeriesVocabularySimple & Compound InterestSBISyllogismsQuadratic EquationsAlgebraQuantitative AbilityScience & TechnologyTabular DataVerbal AbilityData Sufficiency - LRSpot the ErrorMarketingVerbal ReasoningSet TheoryMiscellaneous - VASpeed, Time & DistanceTrigonometryCloze TestComputersBlood RelationsGeneralCoordinate GeometryIIFTArithmetic OperationsRatio & ProportionArrangements & RearrangementsWord BuildingPercentagesCurrent Affairs 2015ParajumblesSymbols & NotationsSSCPlacement TestsUPSCOrder arrangementPassagesProbabilityGREComputer KnowledgeExpansionsPermutations & CombinationsGATEImportant DaysPolityInput - OutputMiscellaneous - LRAuthors & BooksXAT
Practice
0
questions for Free