Thirty men take 20 days to complete a job working 9 hours a day. How many hours a day should 40 men work to complete...
Solution
Number of man hours required to complete the job is
= 30 × 20 × 9 = 5400
Number of hours a day should 40...
Register & Unlock access to Prep for free
Solution
.hez-title-solution{display: none;}
Keynote
#hez-keynote-title{display: none;}
0
Time & Work questions available for your Free Practice
0
Quantitative Ability questions available for your Free Practice
TaglinesNumber SeriesExpansionsNMATIBPSSimple & Compound InterestCATEnvironment & BiodiversityGMATLogarithmsWord BuildingXATPassagesProbabilityQuadratic RelationsMiscellaneous - QAMiscellaneous - GACaselet DIQuadratic EquationsPolityGeneralNumbersCMATTrigonometryParajumblesGeometryVerbal AbilityProfit and LossMixtures and AllegationsMiscellaneous - LRVerbal ReasoningAPPSCCoordinate GeometrySyllogismsArithmetic OperationsMathematical InequalitiesMensurationArrangements & RearrangementsIIFTData Sufficiency - LRComputersData ProblemsRatio & ProportionSBILICSeriesClocks & CalendarsPercentagesDirectionsLine GraphsScience & TechnologyMarketingProgressions & SeriesCircular ArrangementUPSCInput - OutputBar GraphsOrder arrangementCloze TestPie ChartGeneral AwarenessInequalitiesSpeed, Time & DistanceData InterpretationAlgebraTime & WorkNumber SystemPlacement TestsGATECoding & DecodingSSCPermutations & CombinationsMiscellaneous - VAAuthors & BooksBlood RelationsGRESymbols & NotationsFill in the BlanksCurrent Affairs 2015Tabular DataRBILogical ReasoningImportant DaysVocabularySentence ImprovementAveragesSpot the ErrorFunctionsTCSSimple EquationsComputer KnowledgeAnalogiesQuantitative AbilityMATSet Theory
Practice
0
questions for Free