Number of worker days required to complete 2/7th part of the work is
= 250 × 12 = 3000
Number of worker days required to complete...
Register & Unlock access to Prep for free
Solution
.hez-title-solution{display: none;}
Keynote
#hez-keynote-title{display: none;}
0
Time & Work questions available for your Free Practice
0
Quantitative Ability questions available for your Free Practice
Number SystemProgressions & SeriesSSCSentence ImprovementCoding & DecodingOrder arrangementGATESyllogismsNMATVerbal AbilityDirectionsMATPie ChartBar GraphsMensurationData Sufficiency - LRCaselet DITime & WorkInput - OutputSeriesSBIGREXATBlood RelationsParajumblesWord BuildingCATScience & TechnologyProbabilitySet TheoryFill in the BlanksGeometryQuadratic EquationsArithmetic OperationsRatio & ProportionGeneralLogical ReasoningMarketingPermutations & CombinationsCMATUPSCAlgebraNumber SeriesSpeed, Time & DistanceAPPSCRBIGMATGeneral AwarenessTrigonometryMiscellaneous - VAIBPSSpot the ErrorQuadratic RelationsLICCircular ArrangementClocks & CalendarsComputer KnowledgeMiscellaneous - LRLogarithmsVocabularyProfit and LossData InterpretationPassagesMixtures and AllegationsArrangements & RearrangementsPercentagesImportant DaysQuantitative AbilityLine GraphsAnalogiesTaglinesIIFTCloze TestPlacement TestsSimple & Compound InterestTabular DataAveragesPolitySimple EquationsAuthors & BooksInequalitiesExpansionsMathematical InequalitiesNumbersVerbal ReasoningFunctionsComputersData ProblemsCurrent Affairs 2015Miscellaneous - GAEnvironment & BiodiversityTCSSymbols & NotationsMiscellaneous - QACoordinate Geometry
Practice
0
questions for Free