Given 200 men in 50 days complete quater(1/4th) work⇒ 10000 mandays are required to complete 1/4th work⇒ 30000 mandays are required to complete remaining 3/4th workSince in 150 days they need to complete...
Register & Unlock access to Prep for free
Solution
.hez-title-solution{display: none;}
Keynote
#hez-keynote-title{display: none;}
0
Time & Work questions available for your Free Practice
0
Quantitative Ability questions available for your Free Practice
Spot the ErrorOrder arrangementSimple & Compound InterestPolityCurrent Affairs 2015InequalitiesComputer KnowledgeSBICaselet DICMATMiscellaneous - GARBISSCWord BuildingAveragesMixtures and AllegationsSeriesArithmetic OperationsAPPSCTime & WorkSimple EquationsPie ChartLogical ReasoningParajumblesData Sufficiency - LRGREProfit and LossScience & TechnologySyllogismsNMATCoding & DecodingUPSCFunctionsGATELine GraphsData ProblemsGeometryPermutations & CombinationsProbabilityCloze TestGMATRatio & ProportionTCSTabular DataData InterpretationCATLICQuadratic EquationsSymbols & NotationsMathematical InequalitiesXATPassagesIIFTVocabularyAlgebraNumber SystemSet TheoryMiscellaneous - QATaglinesSpeed, Time & DistanceFill in the BlanksNumbersNumber SeriesExpansionsProgressions & SeriesPercentagesQuantitative AbilityVerbal ReasoningPlacement TestsIBPSVerbal AbilityArrangements & RearrangementsBar GraphsSentence ImprovementCircular ArrangementTrigonometryMarketingBlood RelationsImportant DaysMiscellaneous - VAAuthors & BooksMiscellaneous - LRCoordinate GeometryInput - OutputGeneralAnalogiesClocks & CalendarsDirectionsMensurationComputersLogarithmsMATQuadratic RelationsGeneral AwarenessEnvironment & Biodiversity
Practice
0
questions for Free