QUESTION
Q
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds only quarter of the work is done in 50...

Solution

Given 200 men in 50 days complete quater(1/4th) work ⇒ 10000 mandays are required to complete 1/4th work ⇒ 30000 mandays are required to complete remaining 3/4th work Since in 150 days they need to...

Register & Unlock access to Prep for free

Save & Analyse
your Practice

Learn, Practice &
Improve fast

Improve your
Accuracy

Track & Improve
Scores in all Topics

Session Time
Tracker

Review your
Performance

Insights on others
Performance

View Performance
Reports

Achieve your
Target

Flexible Learning &
Practice

Question Time
Tracker

Improve your
exam scores

Solution

.hez-title-solution{display: none;}

Keynote

#hez-keynote-title{display: none;}

 Five-digit numbers are formed using only 0, 1, 2, 3, 4 exactly once. What is the difference between the maximum and minimum number that…

|

Rearrange the following six sentences (A), (B), (C), (D), (E) and (F) in the proper sequence to form a paragraph ; then answer the questions on basis of them. (A) Its prevalence reflects very badly on society that is not able to stop this evil. (B) Though elimination of child labour is an impossible task considering the current socio-economic scenario of these poor families, the Indian government is committed to the…

||||||

In the following question, a part of a sentence is left blank. Choose from the given options, the one which would best fill the blank. The…

|

0 Time & Work questions available for your Free Practice
0 Quantitative Ability questions available for your Free Practice
Practice 0 questions for Free
Scroll to Top