A contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, 2/5th of the...
Solution
Number of man-hours used to do 2/5th of the work is= 25 × 105 × 8 = 21000Remaining work = 1 − 2/5 = 3/5Number of man-hours required to complete 3/5th work is= 21000...
Register & Unlock access to Prep for free
Solution
.hez-title-solution{display: none;}
Keynote
#hez-keynote-title{display: none;}
0
Time & Work questions available for your Free Practice
0
Quantitative Ability questions available for your Free Practice
AnalogiesCATPie ChartGeneralGMATSimple EquationsSyllogismsAveragesProgressions & SeriesSeriesGeneral AwarenessNumbersQuadratic RelationsLine GraphsCoding & DecodingTaglinesMarketingMiscellaneous - QACoordinate GeometryNumber SeriesAlgebraCMATPermutations & CombinationsProfit and LossData Sufficiency - LRAPPSCCaselet DIData ProblemsPolityRBIAuthors & BooksClocks & CalendarsSpeed, Time & DistanceMixtures and AllegationsFunctionsExpansionsPlacement TestsEnvironment & BiodiversityArithmetic OperationsArrangements & RearrangementsVerbal ReasoningDirectionsLogical ReasoningTime & WorkMATPassagesIBPSLogarithmsSpot the ErrorVerbal AbilityXATCurrent Affairs 2015MensurationMiscellaneous - VATCSGeometrySSCComputer KnowledgeNumber SystemQuadratic EquationsIIFTTabular DataSimple & Compound InterestMiscellaneous - GACloze TestGATEParajumblesSBIPercentagesTrigonometryInequalitiesRatio & ProportionProbabilityVocabularyInput - OutputUPSCComputersData InterpretationScience & TechnologyLICCircular ArrangementGRESymbols & NotationsWord BuildingQuantitative AbilityMathematical InequalitiesBar GraphsSentence ImprovementMiscellaneous - LRBlood RelationsImportant DaysSet TheoryFill in the BlanksOrder arrangementNMAT
Practice
0
questions for Free