A can do a work in 12 days. When he had worked for 3 days, B joined him. If they complete the work in 3 more days, in...
Solution
A can complete 1/12th work in one day.
Total number of days A worked = 6 days
⇒ in 6 days he can complete 6 ×...
Register & Unlock access to Prep for free
Solution
.hez-title-solution{display: none;}
Keynote
#hez-keynote-title{display: none;}
0
Time & Work questions available for your Free Practice
0
Quantitative Ability questions available for your Free Practice
PolityEnvironment & BiodiversityPlacement TestsXATVocabularyVerbal ReasoningSimple & Compound InterestSymbols & NotationsIBPSGATESeriesGMATCloze TestArrangements & RearrangementsSimple EquationsMarketingLogical ReasoningAveragesAPPSCLICCircular ArrangementArithmetic OperationsCoding & DecodingData ProblemsCoordinate GeometryData Sufficiency - LRTabular DataRBIData InterpretationMensurationSpot the ErrorLogarithmsIIFTClocks & CalendarsInequalitiesSpeed, Time & DistanceCaselet DIPermutations & CombinationsComputersAlgebraBlood RelationsProbabilityBar GraphsNumbersNumber SeriesSentence ImprovementPassagesTrigonometryTaglinesCurrent Affairs 2015Pie ChartUPSCSyllogismsMiscellaneous - QAProgressions & SeriesFunctionsDirectionsCATMathematical InequalitiesRatio & ProportionExpansionsSet TheoryLine GraphsTime & WorkSBIOrder arrangementWord BuildingParajumblesPercentagesQuadratic RelationsFill in the BlanksMiscellaneous - LRGeneralMiscellaneous - GAImportant DaysGeneral AwarenessNumber SystemTCSVerbal AbilityQuadratic EquationsMATMiscellaneous - VAScience & TechnologyNMATAuthors & BooksComputer KnowledgeQuantitative AbilityGREInput - OutputProfit and LossMixtures and AllegationsAnalogiesGeometrySSCCMAT
Practice
0
questions for Free