A and B can do a piece of work in 72 days; B and C can do it in 120 days; A and C can do it in 90 days. In what time A...

Solution

Let A, B and C complete A1, B1 and C1 work respectively in one day.Given A and B can do piece of work in 72 days.∴ A and B together complete 1/72th part of work in one day.∴ A1 + B1 =...

Register & Unlock access to Prep for free

Save & Analyse
your Practice

Learn, Practice &
Improve fast

Improve your
Accuracy

Track & Improve
Scores in all Topics

Session Time
Tracker

Review your
Performance

Insights on others
Performance

View Performance
Reports

Achieve your
Target

Flexible Learning &
Practice

Question Time
Tracker

Improve your
exam scores

Solution

.hez-title-solution{display: none;}

Keynote

If A can complete a work in N days then A does 1/Nth work in one day.In one day if A does 1/Nth work then A completes...

Of the 10 employees at a certain company, 5 had annual salaries of Rs.20000, 4 had annual salaries of Rs.25000, and 1 had an annual salary…

||||

The customers by opening and investing in the Tax Saver Deposit Account Scheme in a bank would get benefit under _______

||

The usual deposit accounts of banks are

||

0 Time & Work questions available for your Free Practice
0 Quantitative Ability questions available for your Free Practice
Practice 0 questions for Free
Scroll to Top