QUESTION
Q
24 men complete a job by working 7 hours per day for 27 days. 14 men will complete the same work by working 9 hours per...

Solution

Number of men hour days required to complete the work is = 24 × 7 × 27 The number of days required for 14...

Register & Unlock access to Prep for free

Save & Analyse
your Practice

Learn, Practice &
Improve fast

Improve your
Accuracy

Track & Improve
Scores in all Topics

Session Time
Tracker

Review your
Performance

Insights on others
Performance

View Performance
Reports

Achieve your
Target

Flexible Learning &
Practice

Question Time
Tracker

Improve your
exam scores

Solution

.hez-title-solution{display: none;}

Keynote

#hez-keynote-title{display: none;}

In the following question a sentence/part of the sentence is underlined. From the given options select the best alternative to the…

|||||

What will come in place of question mark (?) in the following number series: 7, 13, (?), 49, 97

|||||

In the following question select the option which satisfies the same relationship as found between the two terms on the other side of the…

||

0 Time & Work questions available for your Free Practice
0 Quantitative Ability questions available for your Free Practice
Practice 0 questions for Free
Scroll to Top