24 men complete a job by working 7 hours per day for 27 days. 14 men will complete the same work by working 9 hours per...

Solution

Number of men hour days required to complete the work is = 24 × 7 × 27 The number of days required for 14...

Register & Unlock access to Prep for free

Save & Analyse
your Practice

Learn, Practice &
Improve fast

Improve your
Accuracy

Track & Improve
Scores in all Topics

Session Time
Tracker

Review your
Performance

Insights on others
Performance

View Performance
Reports

Achieve your
Target

Flexible Learning &
Practice

Question Time
Tracker

Improve your
exam scores

Solution

.hez-title-solution{display: none;}

Keynote

#hez-keynote-title{display: none;}

Rearrange the following six sentences (A), (B), (C), (D), (E) and (F) in the proper sequence to form a paragraph ; then answer the questions on basis of them. (A) Its prevalence reflects very badly on society that is not able to stop this evil. (B) Though elimination of child labour is an impossible task considering the current socio-economic scenario of these poor families, the Indian government is committed to the…

||||||

STP in marketing means

|

In a market 4 men are standing. The average age of the four before 4 years is 45, after some days one man is added and his age is 49. What…

|||||

0 Time & Work questions available for your Free Practice
0 Quantitative Ability questions available for your Free Practice
Practice 0 questions for Free
Scroll to Top