Let,
The work done by a man in a day be = m
The work done by a woman in a day be = w
2 men and 1 woman can complete a piece of work in 14 days.
Therefore,
14(2m + 1w) = 1
28m + 14w = 1...
Register & Unlock access to Prep for free
Solution
.hez-title-solution{display: none;}
Keynote
#hez-keynote-title{display: none;}
0
Time & Work questions available for your Free Practice
0
Quantitative Ability questions available for your Free Practice
MensurationGATEPie ChartPassagesImportant DaysLogical ReasoningMiscellaneous - LRScience & TechnologyAPPSCInequalitiesMarketingSyllogismsMixtures and AllegationsArrangements & RearrangementsPercentagesGeneralTCSMiscellaneous - GAAuthors & BooksLICSpot the ErrorPlacement TestsNumber SystemIBPSMiscellaneous - QAEnvironment & BiodiversityTime & WorkParajumblesVocabularyAlgebraRBIProfit and LossPermutations & CombinationsData Sufficiency - LRComputersPolitySimple & Compound InterestDirectionsAnalogiesFill in the BlanksGMATSSCSymbols & NotationsInput - OutputMathematical InequalitiesCMATVerbal ReasoningMiscellaneous - VACoordinate GeometrySentence ImprovementClocks & CalendarsData ProblemsNumbersQuadratic EquationsTabular DataCircular ArrangementVerbal AbilityNumber SeriesArithmetic OperationsTaglinesTrigonometryProgressions & SeriesOrder arrangementBlood RelationsProbabilityData InterpretationExpansionsSpeed, Time & DistanceLogarithmsSeriesMATGRECoding & DecodingQuadratic RelationsCATXATCloze TestIIFTBar GraphsQuantitative AbilityComputer KnowledgeFunctionsSet TheoryAveragesCaselet DIUPSCGeometryNMATGeneral AwarenessRatio & ProportionLine GraphsSBISimple EquationsWord BuildingCurrent Affairs 2015
Practice
0
questions for Free