12 men construct 1.5 km of road in 7 days. 28 men will construct 12 km of road in how many days ?

Solution

Number of mendays required to construct 1.5 km of road is = 12 × 7 = 84 Therefore number of mendays required to construct 1 km...

Register & Unlock access to Prep for free

Save & Analyse
your Practice

Learn, Practice &
Improve fast

Improve your
Accuracy

Track & Improve
Scores in all Topics

Session Time
Tracker

Review your
Performance

Insights on others
Performance

View Performance
Reports

Achieve your
Target

Flexible Learning &
Practice

Question Time
Tracker

Improve your
exam scores

Solution

.hez-title-solution{display: none;}

Keynote

#hez-keynote-title{display: none;}

Which of these is not a means of personal communication on the internet ?

|||

Directions : Study the following information carefully and answer the questions that follow. Out of the 15,000 candidates eligible for an Officer’s post in a Public Sector Bank, 450 candidates have prior experience of working in Public Sector Banks in rural areas only. 25% of the total number of candidates have prior experience of working in…

|||

Find the relation between x and y based on the given equations i) 6×2 − x − 12 = 0 ii) 6y2 + y − 15 = 0

||||||

0 Time & Work questions available for your Free Practice
0 Quantitative Ability questions available for your Free Practice
Practice 0 questions for Free
Scroll to Top