Number of child days required to complete a piece of work is = 12 × 21 = 252 child daysNumber of children...
Register & Unlock access to Prep for free
Solution
.hez-title-solution{display: none;}
Keynote
#hez-keynote-title{display: none;}
0
Time & Work questions available for your Free Practice
0
Quantitative Ability questions available for your Free Practice
Line GraphsNMATSymbols & NotationsRBIEnvironment & BiodiversityTCSExpansionsGMATCoordinate GeometryIBPSInequalitiesNumber SeriesSyllogismsUPSCAuthors & BooksCaselet DIMixtures and AllegationsCATVerbal ReasoningLICMiscellaneous - LRArrangements & RearrangementsVerbal AbilityAPPSCInput - OutputBlood RelationsGeometryGATEFunctionsAlgebraComputer KnowledgeTabular DataXATMiscellaneous - GAImportant DaysLogarithmsData InterpretationPermutations & CombinationsGeneralIIFTSpeed, Time & DistanceMensurationSentence ImprovementTrigonometryData Sufficiency - LRRatio & ProportionCurrent Affairs 2015PassagesPolityQuantitative AbilitySet TheorySeriesGeneral AwarenessNumbersPercentagesCloze TestQuadratic EquationsSpot the ErrorCMATGREMiscellaneous - VAMiscellaneous - QABar GraphsData ProblemsPie ChartComputersArithmetic OperationsTaglinesDirectionsSimple EquationsMarketingMATTime & WorkOrder arrangementPlacement TestsMathematical InequalitiesAveragesParajumblesScience & TechnologyCircular ArrangementCoding & DecodingQuadratic RelationsAnalogiesProbabilityFill in the BlanksClocks & CalendarsProgressions & SeriesVocabularySimple & Compound InterestProfit and LossNumber SystemSBISSCLogical ReasoningWord Building
Practice
0
questions for Free